portfolio
Rockport
- Project Area: 4963 Sq. ft.
- LOD: Trades Floor Finish
- Software: AutoCAD
41 Bank St
- Project Area: 1996.2 Sq. ft./ 2368 Sq. ft.
- LOD: Trades Front Elevation
- Software: AutoCAD
Hubbard Powis
- Project Area: 1996.2 Sq. ft./ 2368 Sq. ft.
- LOD:
- Trades Covered: Lighting
- Software: AutoCAD
Haviland
- Project Area: 4771.32 Sq. ft.
- LOD:
- Trades Covered:
- Software: AutoCAD
Spillway Bridge
- Project Area:
- Architect: N/A
- Engineer: N/A
- Contractor(S): N/A
- Owner: N/A
- LOD:
- Trades Covered: AS BUILT
- Software: MicroStation
- Verticals: 2023
Bank Daze
- Project Area:
- Architect: N/A
- Engineer: N/A
- Contractor(S): N/A
- Owner: N/A
- LOD:
- Trades Covered: AS BUILT
- Software: AutoCAD
- Verticals: 2021
Eufaula Replace Spillway Bridge
- Project Area:
- Architect: N/A
- Engineer: N/A
- Contractor(S): N/A
- Owner: N/A
- LOD:
- Trades Covered: AS BUILT
- Software: MicroStation
- Verticals: 2023
Communities In Schools Central Texas
- Project Area: 6085 sq ft
- Architect: N/A
- Engineer: N/A
- Contractor(S): BIM SERVICES LLC
- Owner: N/A
- LOD: 350
- Trades Covered: Plumbing, Shop Drawing, As -Built
- Software: Revit Fabrication 2021
- Verticals: Plumbing
Challenges and Solutions
Challenge 1: Ceiling Space Constraints
- Issue:
- Condensate drain pipe clashed with ceiling and fire protection pipes below ceiling.
- Solutions:
- Drop ceiling to accommodate pipes.
- Use a pump for condensate drain at units.
- Reduce pipe run length by dropping pipe into nearest mop sink.
Challenge 2: Exposed Plumbing Risers in Rooms
- Issue:
- Plumbing risers exposed or in the middle of rooms per design.
- Solution:
- Coordinate and reroute plumbing pipes to conceal or relocate them appropriately.
Mardela Middle & High School
- Project Area: 118,993 sq ft
- Architect: N/A
- Engineer: N/A
- Contractor(S): Not specified
- Owner: Not specified
- LOD: 400
- Trades Covered: Plumbing, Shop Drawing, As-Built
- Software: Revit Fabrication 2021
- Verticals: Plumbing
Challenges and Solutions:
Challenge 1: Coordination in Corridors
- Issue:
- Congested corridors with units, refrigerant pipes, light fixtures, and fire protection (FP) systems.
- Solution:
- Relocated units to adjacent rooms to clear space in corridors, resolving clashes with other trades. Changes were submitted for approval.
Challenge 2: Concurrent Modeling and Fieldwork
- Issue:
- Modelling, coordination, and drawing submissions overlapped with fieldwork, posing challenges for accuracy and documentation.
- Solution:
- Implemented a ‘Deliverable Log’ to track revisions and provide links to the latest drawings/models. Mobilised resources to ensure timely and accurate delivery of multiple deliverables to the client.