Williston Public Safety Facility

Williston Public Safety Facility
  • Project Area: 22,561 SF
  • Architect: Smith Alvarez Sienkiewycz
  • Engineer: N/A
  • Contractor(S): BIM Services LLC
  • Owner: N/A
  • LOD: 400
  • Trades Covered: Fire Protection, Shops
  • Software: Revit Fabrication 2021
  • Verticals: Fire

 

Challenges and Solutions:

Challenge 1: Ceiling Space Optimization

  • Issue:
    • Limited ceiling space necessitated strategic planning for trade hierarchy and efficient utilization.
  • Solution:
    • BIM Services prioritized trades requiring access (such as cable trays, valves, dampers) closer to the ceiling, and suggested reroutes for better coordination and value engineering.

Challenge 2: Elevation of Fire Protection (FP) Pipes

  • Issue:
    • Critical elevation considerations for FP main pipes to ensure system efficiency and compliance with city regulations.
  • Solution:
    • BIM Services proposed optimal elevation and routing of FP mains, avoiding rigorous drops and offsets that could trap water and impact system approval, ensuring maximum efficiency.

Gallery

FAQS:

Answers That Build Clarity

No FAQs found.

BIM enhances construction by enabling accurate planning, real-time collaboration, and clash-free coordination. It helps project teams visualize each stage before construction begins, improving scheduling, cost estimation, and risk management. Contractors, architects, and engineers rely on BIM modeling services to deliver projects faster, with fewer changes and lower costs.

Thank you

You've been successfully unsubscribed.