Williston Public Safety Facility

  • Project Area: 22,561 SF
  • Architect: Smith Alvarez Sienkiewycz
  • Engineer: N/A
  • Contractor(S): BIM Services LLC
  • Owner: N/A
  • LOD: 400
  • Trades Covered: Fire Protection, Shops
  • Software: Revit Fabrication 2021
  • Verticals: Fire

 

Challenges and Solutions:

Challenge 1: Ceiling Space Optimization

  • Issue:
    • Limited ceiling space necessitated strategic planning for trade hierarchy and efficient utilization.
  • Solution:
    • BIM Services prioritized trades requiring access (such as cable trays, valves, dampers) closer to the ceiling, and suggested reroutes for better coordination and value engineering.

Challenge 2: Elevation of Fire Protection (FP) Pipes

  • Issue:
    • Critical elevation considerations for FP main pipes to ensure system efficiency and compliance with city regulations.
  • Solution:
    • BIM Services proposed optimal elevation and routing of FP mains, avoiding rigorous drops and offsets that could trap water and impact system approval, ensuring maximum efficiency.